Genser Energy signed a power purchase agreement with Abosso Goldfields Limited, a subsidiary of Gold Fields, for the delivery of power to its Damang Gold Mine, a higher-grade gold mine located in the Prestea-Huni Valley district of the Western Region of Ghana.

The Damang plant is a gas turbine plant originally commissioned in November 2016. The Damang plant currently runs on natural gas via the Genser Energy pipeline. Further expansion works are underway that will convert the plant to a combined cycle gas turbine configuration and connect it to the high voltage network.

We are also working with our client to facilitate the conversion of their heavy mobile equipment from heavy hydrocarbons to natural gas fuels.

Damang plant on top of a raised area adjacent to a lake